מצרים וסעודיה במגעים מתקדמים לחיבור רשתות החשמל
26/06/2019 21:33

מצרים וסעודיה במגעים מתקדמים לחיבור רשתות החשמל שלהן בפרויקט שעלותו כ- 2.5 מיליארד דולר.

Egypt and Saudi Arabia have agreed to set a timetable for the implementation of the electricity link project between the two countries next month. Government sources told Daily News Egypt that intensive meetings were held over the past two months to follow-up on the technical parts of amending the tracks of the Saudi land link. This is after amending it for the implementation of the Neom project.

A consultant will be chosen to carry out the maritime survey of the submarine cable tracks before the end of August. The sources added that the next meeting between officials from Egypt and Saudi Arabia will see an agreement on the implementation timetable, awarding standing tenders, and setting a deadline for the pilot phase operation. The first quarter of 2020 will see the first phase of the project.

The sources pointed out that the tender offered earlier included different routes and other locations. In view of the implementation of the project, Neom, the tracks of the electrical connection line have been modified, which necessitates a tender with new specifications. The project connects the two power networks in Egypt and Saudi Arabia to a 500kV transformer from the Badr transformer substation in Egypt to a transfer station east of Medina, through the Tabuk station in Saudi Arabia with a length of 1,300km, of which 820km in Saudi Arabia and 480km in Egyptian land.

The total cost of the project was $1.6bn but after adjusting the tracks and changing the prices of the electrical tasks, the total value of the implementation of the electricity interconnection between Egypt and Saudi Arabia will reach $2.5bn.

Daily News Egypt | Mohamed Fatag | 22.6.19